Agenda item

TWC/2010/0828 - Land at Ironstone, Lawley, Telford, Shropshire

Minutes:

This was an application for the variation of condition 16 of outline planning permission W2004/0890 to exclude the areas comprised within the reserved matters application ref TWC/2010/0627 and within plots G4 and G5 as defined within the phasing plan drawing number 006 rev L from the effect of condition 16 (amended description) and land at Ironstone, Lawley, Telford, Shropshire.

 

The Planning Officer advised Members that a request had been brought before Members in order to vary the affordable housing element of Lawley Phase 10 urban extension.  The developers sought permission from the Authority to agree a zero percent affordable housing. The developers would be seeking to apply for Homes England Funding which could provide 10% affordable housing on site.

 

At their 30 June 2021 meeting, Members resolved to grant the Deed of Variation to secure the provision of 10% affordable housing on site.  It was established that the resolution that was agreed on 30th June, based on the update to Planning Committee, could not be implemented and that the request from the applicant had been misinterpreted. The correct request was outlined within the report.. 

 

Councillor J Yorke spoke against the application on behalf of the Parish Council who raised concerns regarding zero percent affordable housing and the incorrect information presented to the 30 June Committee.  He raised at that Committee that the Developers had endorsed the ten percent affordable housing and the Parish Council reluctantly accepted this due to paragraph 64 of the NPPF which requires at least ten percent affordable housing contribution.  He raised further concerns regarding the incorrect information, performance, the viability and the affordable contribution, the profitability of the development and the lack of assurance regarding the Homes England Grant.   He said that the requirement from the 2005 application for twenty five percent affordable housing will no longer materialise together with the grant of the community facility.  He said that there had been continued failures and that applications should be heard upon planning merit and adherence to policy and conditions.

 

The Planning Officer explained that since the economic downturn the consortium of Developers had found it necessary to reduce the number of affordable dwellings on phases approved since 2008.  Viability evidence had been presented to the Committee on the land value today which showed that Phase 10 was unviable and even without affordable housing the development would still not provide the financial return that would meet the guidance set out in the NPPF.  The viability report had been assessed by an independent consultant who supported the applicant’s position.  The developers were seeking to provide 10% affordable housing on the site via Homes England which would result in the delivery of four less affordable units. However, in order for the development to be eligible for the Homes England funding, these could not be obligated through S106 or condition, and the Local Authority must first agree to zero percent affordable housing through planning obligation. Taking all of the information into consideration officers accept the applicant’s justification that the S106 obligations as approved were unviable in respect of Phase 10 and needed to be reconsidered in order to bring forward the site and prevent it stalling.  Officers considered that the benefits would significantly outweigh harm and it was recommended that the reduction to the affordable housing be approved.

 

During the debate some Members raised concerns regarding the true representation of the facts and figures and that they felt they had been “backed into a corner” and “held ransom” with regards to affordable housing.  Other Members felt that there would always be a change of land value and that this should have been taken into account, the lack of up to date figures in the reports, lack of garage space and electric charging point.  There was a suggestion of an incentive scheme for affordable housing.  The position was also queried regarding how the land cost was taken into account in the viability appraisal; was it based on its current value or the value in 2005 and how it was considered with the continual increase in land value?  Some Members asked if the application was refused would the site be left vacant and an eyesore with no dwellings.  They recognised that housing was needed and required by Government guidelines and Members felt that they were stuck between a rock and a hard place.  Other issues raised by Members included whether there had been an over-estimation of costs, whether the cost of re-building of the wall should have been taken into consideration and had the costs been spread over all of the phases of the development.  Some Members felt frustrated with the change of circumstances but felt they had no legal room to refuse the application.

 

The Planning Officer explained again that the 30 June 2021 committee report stated that there would be 10% affordable housing but that it should have referred to zero per cent and that the 10% may be provided by the Homes England Funding.  At section 6.33 of the report it showed the developers would be in deficit even with zero percent affordable housing contribution.

 

The Development Management Service Delivery Manager confirmed that the original June Report stated that there would be zero percent under the S106 and that the 10% could come forward through the Homes England Grant Funding at a later date. She explained that an update report was then presented to Committee and it later became apparent that the update report contained erroneous information which Members had resolved to approve.  Independent advice was sought with regards to viability and the information had been assessed and, in relation to the land value changes, the development could no longer facilitate the affordable housing contributions coming forward through the S106 agreement.   Costs of construction had increased and there had been some remediation and redesign issues on the site.  There was a residual value framework that had to be considered which looked at the enhanced value from sustainability and design standards of the site.  It also looked at the development land, profit and cumulative policy costs, infrastructure contributions and mitigation of the impact of the development.  The Service Delivery Manager confirmed that whilst house values had risen, so had the cost of construction such as the price of steel and timber which had significantly increased.  Queries would have to be referred back to the independent assessor so answers to Members questions would not be available during the meeting.  The viability assessment had not changed from the Committee held on 30 June 2021 in that the site could not afford to offer any affordable housing.

 

The Legal Advisor confirmed that the viability report was a technical report and viability was a recognised material consideration.  If Members were minded to refuse the recommendation it did create a difficulty for officers in the event of an appeal to the Planning Inspectorate.  If Members’ refusal was based on an objection to the viability report, on what grounds would the rejection be based.  Viability was a material consideration.  His advice to Members was that the viability report would be given weight at an appeal.  The Legal Advisor felt that, without evidence, the Committee were not in a position to question the viability report as it was a technical report based on technical grounds and it would be technically difficult to challenge.  He suggested to Members that if they felt they had questions that still needed to be answered and they required further information that they may ask for a deferment of the application.

 

The recommendation as follows was proposed and seconded.

 

“It is recommended that the Deed of Variation to the Section 106 Agreement be approved”

 

And upon being put to the vote, it was by a majority defeated.

 

The Chair asked Members to consider their reasons for not supporting the application.

 

A motion was put forward that the application be deferred in order for Officers to address the questions members raised on the viability report and for the item to be reported back to Committee.  It was proposed and seconded that the application be deferred to the September meeting.

 

Upon being put to the vote it was, by a majority:

 

RESOLVED – that further consideration of this application be deferred in order to allow officers and the applicant opportunity to provide additional clarification on matters raised by Members in relation to the viability report and the delivery of affordable housing.

 

Supporting documents: